Concrete Calculator

Estimate cubic yards, bag count, and cost for any slab, footing, column, or post hole pour — then see instantly whether bagged concrete or ready-mix delivery is the cheaper option for your job.

Concrete Calculator
Pour dimensions
ft
ft
in
%
Edit local pricingOptional
$/yd
$
$
$
$
Pour preview
10.0 ft10.0 ft4.0 in

Hover faces for area • thickness exaggerated for visibility

Recommended buy
Ready-Mix Delivery
1.5 cu yd · $362.50
Volume Needed
36.7 cu ft
1.36 cu yd (incl. 10% waste)
Best Estimate
$362.50
1.5 cu yd
Purchase OptionQuantityEst. Cost
Ready-Mix DeliveryBest value1.5 cu yd$362.50
40 lb Bags123 bags$553.50
60 lb Bags82 bags$492.00
80 lb Bags62 bags$480.50
Cheapest option: Ready-Mix Delivery at $362.50For pours under ~1 cu yd, bags are usually cheaper and easier to transport. For anything above roughly 1 cu yd, ready-mix delivery is typically cheaper per yard and far less labor.
This order likely qualifies for a short-load feeMost ready-mix suppliers charge an extra fee (typically $75–150, already added above as $100.00) for deliveries under 3 cubic yards — it costs them almost the same to send a truck regardless of load size. Call your supplier to confirm their exact minimum and fee before ordering.
This is a material estimate only. Always add extra for uneven subgrade, spillage, and order a buffer — running short mid-pour is far costlier than a little leftover mix.

How to Calculate How Much Concrete You Need

Concrete is ordered by volume, not by surface area — so before you call a ready-mix supplier or load up on bags, you need to convert your project's dimensions into cubic feet or cubic yards. The formula depends on the shape you're pouring.

Slabs, Footings & Rectangular Pours

Multiply length by width by thickness (converted to feet), then divide by 27 to get cubic yards:

  • Volume (cu ft) = Length (ft) × Width (ft) × Thickness (ft)
  • Cubic Yards = Volume (cu ft) ÷ 27

Example: a 10 ft × 10 ft slab at 4 inches (0.33 ft) thick = 33.3 cu ft, or about 1.23 cubic yards.

Round Columns & Post Holes

Use the cylinder formula, converting the diameter to a radius in feet:

  • Volume (cu ft) = π × Radius² × Height

Example: a 12-inch diameter post hole (0.5 ft radius) that's 3 ft deep = π × 0.5² × 3 ≈ 2.36 cu ft.

Always Add a Waste Factor

Real job sites are never perfectly flat, and every pour loses some mix to spillage and form seepage. Add 5-10% to your calculated volume for simple slabs, and 10-15% for irregular shapes, sloped grades, or a hand-mixed pour. Running short mid-pour means a visible cold joint and a rushed second batch — always round up.

Concrete Bag Yield Reference

If you're mixing by hand or with a small mixer, here's how much finished concrete each bag yields:

Bag SizeYield (cu ft)Bags per Cubic Yard
40 lb bag0.30 cu ft~90 bags
60 lb bag0.45 cu ft~60 bags
80 lb bag0.60 cu ft~45 bags

Ready-Mix vs. Bagged Concrete: Which Is Cheaper?

As a rule of thumb, bagged concrete makes sense for anything under about 1 cubic yard — post holes, small footings, repairs, and steps. Once you cross roughly 1 cubic yard, ready-mix delivery almost always wins on cost per yard, and it saves substantial labor since you're not hand-mixing 40+ bags. Most ready-mix suppliers also have delivery minimums (often 1 yard), so factor that in for very small pours.

Tips for a Successful Concrete Pour

  • Order 5-10% more than your calculated volume — a short pour is far more expensive to fix than a little leftover mix.
  • Check your local frost depth before setting footing depth; codes vary significantly by region.
  • Have your forms, rebar, and finishing tools ready before the truck arrives — ready-mix starts setting fast.
  • Wet the subgrade lightly before pouring in hot weather to prevent the ground from pulling moisture out of the mix too quickly.
  • Plan your control joints (roughly every 8-10 ft for slabs) to manage cracking.

Frequently Asked Questions

How much concrete do I need for a 10x10 slab?

For a 10 ft x 10 ft slab at the standard 4-inch thickness, you need about 1.23 cubic yards (roughly 33 cu ft) before waste. Add a 10% waste factor and you'll want to order about 1.35 cubic yards, or plan for around 92 bags of 60 lb pre-mix.

How many 80 lb bags of concrete make a yard?

One cubic yard of concrete requires about 45 bags of 80 lb pre-mix concrete, since each 80 lb bag yields roughly 0.6 cubic feet and a cubic yard is 27 cubic feet.

How thick should a concrete slab be?

A typical shed or patio slab is 4 inches thick. Driveways and slabs supporting vehicles are usually poured 5-6 inches thick. Footings vary by frost depth and local code — check with your municipality.

Is it cheaper to buy bagged concrete or ready-mix?

For small pours (roughly under 1 cubic yard) bagged concrete is usually cheaper once you factor in ready-mix delivery minimums. For larger pours, ready-mix delivered by truck is almost always cheaper per yard and saves significant labor.

How much waste factor should I add to a concrete order?

Most contractors add 5-10% waste to account for spillage, an uneven subgrade, and form leaks. Complex shapes or a hand-mixed pour on rough ground should use closer to 10-15%.